The project continues! Although I was so late with Week 10 that I decided to combine weeks 10 and 11. As you will see from this post – a lot went on from September 19-October 2, 2021. Some of it involved construction, some not – as you will see. I’ll do my level best to make this interesting by including not only some construction photos, some other stuff, to include golf and a bit of hobbies!
There are a lot of pictures here – click on any of them for a bigger view.
Let’s start with electrical work and some progress around the cellar. Wait, the cellar? Why there? Aren’t you building a new garage and house deck Mark? All valid questions that I am presupposing that you may be asking! So let me attempt clarification.
To power the new building, I needed to get the service upgraded from 100 amps to 200 amps. Our electrical service meter and box was in the back of the house over the old (now removed) house deck. Previously, electrical power came from the National Grid pole out front on the street to the house then went along the soffit and into the cellar at the back right-hand corner of the house if you will. The plan was to make this bigger and better by moving the meter and building a new box for it at the front left corner of the house. A new hole had to be drilled for the new power cable, and that needed to be run to a new replacement distribution box in the basement. This work occurred on September 21st.


Drilling through the old sill was a bitch. The sill was quite thick – 13″ – and made of solid oak. The hole drilling destroyed two hole saw bits.

Outside, work went on the new meter box and running the cable and hooking it up to the power grid.

Back in the cellar, the old distribution box mounting monstrosity was removed and a new sheet of plywood and some lumber from the garage build was used to build a suitable mount. The new configuration is bigger and we will need to move the dryer to the wall to the left of the distribution box so that the vent hose is not right next to it. But, as we were using the old the shelves I never got around to paint it as you can see – and it looked like hell.
Also, I need to back up a bit. It had been necessary for me to clear a lane along the wall for the electricians to run the power cable prior to their starting work. After I did that, I got a good chance to look at the wall and the crappy homemade shelving/cabinet. I noticed a lot of old paint flaking on the wall near the dryer vent and some puckering where I had painted the corner in the front left of the house. The puckering was due to efflorescence, not water leaking, even with the excessive rain we have had this summer. An old dry well that I had built over a decade ago in the front left corner of the house was no longer doing its job, so the rain water outside the basement wall was not properly draining – leading to the efflorescence bubbling up behind the paint. We decided that the shelving cabinet needed to go and the wall repainted.
Before I did that, I rebuilt the drywell. When I originally built it, I had dug down about 3 feet and hit sand, so I had then assumed that the soil was free-draining. When I dug this time, I went a bit deeper, and to my surprise I found that there was yet another soil layer under the sand. This one was a loamy clay – that does not drain well. So, I dug down another 3 feet and backfilled it all with sand from the excavations in the backyard. I replaced the downspout extensions and doubled the length. The we covered the area with a filter fabric and then covered that with river stones.
I then spent the time to take down the shelving/cabinet with my wife. She was able to recycle the doors as shelving in another section of the cellar. I scraped off any flaking paint and exposing any efflorescence. Then, I used a mildly acidic product, Drylok Etch, across the wall to clean and prep for painting with bright white Drylok Extreme (both from Home Depot). This took a while, but came out well. We are taking the opportunity to clear out some stuff and have a yard sale this weekend to get some new homes for some good stuff we don’t need anymore. Plus, I can’t do any hobbies as you can see below!
Back in the garage, the septic line was stubbed up in the floor with a cleanout.

On the 24th, it was time to place the concrete floor in the garage. I say “place” and not “pour” because that was drilled into me in the US Army Corps of Engineers as the appropriate terminology – and that stuck.
Installing the vapor barrier (ok a sheet of plastic over the compacted sand). The plastic is secured, and the steel is wired together.

This was no problem as this plywood will be removed eventually when the door is installed.
Concrete truck delivering. Working the concrete. Then the sky opened up… …necessitating a temporary rain cover. Final finishing.
Because of the many rain days, Andy Cormier arranged to get help to finish off the septic line installation.
Having the septic line in the ground and attached to the septic tank allowed for its backfilling as well as work to proceed on the driveway excavation.
On Monday, September 27th, Lynn and I participated in the annual West Point Society of New England’s annual charity golf tournament, along with our friends, Lisa and Jim Kularski. This year, the beneficiary was Homes for our Troops. It was a nice break while construction work continued.
When we returned home, there was a lot of dirt moved around. It turned out that the soil under the driveway had the same layering issue that I found in my dry well excavation – so a lot had to go, and be replaced with clean fill.


Of course, Tuesday the 28th brought yet more downpouring rain. Therefore, earthwork and any other work could not happen. We only got a delivery of deck material for the house deck.

On Wednesday the 29th, the skies cleared and work could proceed. The driveway was excavated and brought to grade. Old asphalt, and interfering roots and stumps (including a 4-5 ton maple tree stump) were removed in this process.
Asphalt removal Massive stump!
At the end of the day, the driveway was filled, and all the holes were filled in.



The next work skipped a day (rain), and that involved the framing of the replacement house deck. This was October 1st. Jonny also got ready to install the rain gutter system for the garage deck.

To make up lost time to rain, work continued on the deck on Saturday the 2nd. This weekend I had not one but two competitive golf tournaments. The first was on Saturday which was the Finals of the Tour of the Brookfields. If you are on Facebook, the group link is here. I am a member of the committee. My team was in the lowest division, but we did not come in the top three. Still, congrats to the winners!

After the tournament, I returned to see progress on the house deck.


So, a lot of progress was made over the two weeks!
(Lastly, I previously mentioned a couple things that I need to circle back to – the first being the Sunday Founder’s tournament at Quail Hollow Golf and Country Club (where I am a member). This was an individual event and I played better, but not well enough to be the winner (only one male and one female winner out of dozens of players so no big deal). However, back during the annual club championship (a two-day 36-hole tournament of individual medal play from the back tees) on July 31-August 1st – I was able to play my best golf of the year (98/88 for a net 2 over par for the event) and win the D flight against 11 others. So Sunday, I got my reward.

What you see here left to right is a comic statue that belonged to my grandfather Marcus (a WWII vet who gave me a love of golf), my unlucky conquistador “Franco”, my trophy, and as it’s October, my Halloween mini-diorama with Ral Partha 25mm figures of classic monsters from the 30’s Universal Studios movies.
Ah, but I digress – week 12 is well underway and I will have much more to share. I hope that you enjoyed this and thanks for looking!
WOW…construction, golf, more construction, more golf…and then some unexpected digging and painting. You have been very busy.
Great to see that the garage is full steam ahead, and also that progress is being made on all fronts. As for the painting of miniatures, I say…play golf while the weather permits. 🙂
LikeLiked by 3 people
Thanks Anthony! Yes, the days seem to fly by, and hopefully I will get back to miniatures soon. Winter is indeed coming, which is a challenge for the build as well.
LikeLiked by 2 people
Really taking shape now Mark and so much more has been done. Glad to see you are finding time for other stuff too like golf. All in all it’s going to be quite some place once finished. I’m sure you must be pleased with how things are going. Look forward to catching up in due course. 🙂
LikeLiked by 3 people
Cheers Dave! And still so much more to do – the pandemic has not been great on supply chains for sure.
LikeLiked by 2 people
Great how all these extra jobs are getting done while the work is taking place as well Mark. The deck is looking good, and all the utility work is progressing well and will be a great upgrade while moving forward.
Congratulations on the trophy Mark, and finding the time to take part in some tournaments.
LikeLiked by 3 people
Thanks Dave. Seems like one area of work unmasks another in need of attention. But, forward progress is good as you say. Still, I miss my hobbies! Though I guess golf counts there too. As for the trophy, that doesn’t happen often so I definitely wanted to show that! Cheers!
LikeLiked by 2 people
Busy time mate. It’s progressing well. Nice trophy 😉
LikeLiked by 3 people
Cheers pal
LikeLiked by 1 person
More progress is always a good thing, I was beginning to worry I’d missed a post as it seem a long time since the last one (and it turned it was).
Nice to see you getting to play some golf, and legs on show too!!
We even had some figures on show at the end of the post! 😉
Cheers Roger.
LikeLiked by 3 people
Thanks Roger, it was a hectic couple of weeks both for the project and for life in general. As for legs, well, I concur! I’m definitely hoping to get back hobbying soon too. All the best!
LikeLiked by 2 people
Looking good there Mark- looks to have been a lot of progress done.
Will have to remember to place not pour concrete in the future.
Cheers,
Pete.
LikeLiked by 4 people
Looked as if I saw a few two woods there and maybe a couple of (back seat) drivers?
LikeLiked by 3 people
Ha!
LikeLiked by 2 people
Every discipline has its own lingo and quirks to be sure. Cheers Pete!
LikeLiked by 3 people
The man cave is coming along great.
LikeLiked by 3 people
😀
LikeLiked by 1 person
Its great to see more progress but I enjoyed seeing the trophies the most. They are all cool pieces that tell us something about you, if you know what I mean!
LikeLiked by 3 people
Thanks man!
LikeLiked by 3 people
Still seems like it’s all good progress! 🙂 Nice to see you enjoying your golf as well!
LikeLiked by 2 people
Lovely post mate! great progress photos just the thing for an old guy like myself likes, one forgets the improvements one does, bloody handy records that will aid future folk that may end up purchasing your property in the future, it can only add value you place and give future buyers confidence that the work wasn’t shonky, something i’m afraid is happening over here!
LikeLiked by 1 person
Another entertaining construction read!
LikeLiked by 1 person