Our Garage+ Project – Week Nine Update

Last week (September 12-18, 2021) was unfortunately the slowest progress week to date. Gravel was spread under the new house deck location and some more asphalt was removed there as well. We also got our first plumber visit and a lot of action is happening that is not actual construction.

For example, we were able to get a visit from Door Systems of Worcester so that we could evaluate options and order a garage door. The bad news is that that door will take 3 months to arrive. COVID-19-related delays are a factor beyond anyone’s control.

The Victors measure for the gravel.
The gravel is placed.

This week should prove to be more active – Andy Cormier is back from vacation, so digging will recommence on the sewer line and the driveway. And much electrical work will be happening, with our service upgrade (needed for the new building demands and more) as well as some plumbing too.

Thanks for staying with me. I turned 59 this week, so I still believe that this project will get done before I turn 60!

Tabitha got me some practice foam golf balls – her favorite color – purple. Well, she also likes pink, but I’m glad she didn’t go down that route!

Hope to show you all more next week!

Our Garage+ Project – Week Eight Update

The project continues into week #8. This week, with Labor Day on Monday, was a short one, but work did get done. If you remember, this project also includes work on our back yard, driveway, and back deck. This is the deck attached to the house – as opposed to the one attached to the garage. It will be bigger and more functional than the current one. Foot traffic into the house will be rerouted and the driveway reconfigured here.

A longitudinal view of the existing house deck on Tuesday. Access will be rerouted as you will see below.
Lateral view of the existing house deck on Tuesday. We had some flowers here but did not really do much gardening-wise here this year as the renovation was coming. I say “we” but that is Lynn’s purview – not mine…she does that work (as she would tell you). She’s actually superb at landscaping. And mowing the lawn – but that’s because she forbids me to do it. Seriously!
The plan for the house deck as seen from a CGI view of the new deck off of the new garage building – though the decking color plan is for gray not brown. In addition to the new access means to the back door, we also will be adding paving stones to make walkways connecting the two buildings (not shown here).

Given the amount of previous work done, there was a need to reorganize the site a bit on Tuesday September 7th and Wednesday September 8th. Excess materials were returned for credit and site trash and leftover pieces of “stuff” (shingles, lumber, plywood, etc.) were picked up and carted away.

Tuesday morning saw Ready Installs loading up the excess roofing shingles for credit.

On September 9th, work on the back deck went into high gear. It was removed and carted away.

Rail removal on the house deck.
The decking is removed and now the joists and end plates are ready to go.
Deck is gone!

Surprisingly, there was an old asphalt landing under the dirt here that I found while removing a decades worth of leaves that had blown through the lattice found a home under our mudroom!

Cleaned up and ready for the piers. Note the old found asphalt landing.
Lateral view with deck removed.
View towards the new garage building.

On Thursday September 9th, the father and son team from Ready Installs (Jon and Jonny Victor) measured for the new piers for the house deck. Later on Thursday, it rained a lot – AGAIN.

Meanwhile Mike Astrella (electrician) was busy getting light positions chosen, as well as working on the rough electrical for both the upstairs and downstairs of the new building.

On Friday, I made a few supply runs to Home Depot in Auburn and EW Electrical Wholesalers in Worcester to get overlooked electrical supplies and materials.

Hitting Home Depot!

Also on Friday, the house deck piers arrived.

Piers being moved to the back by Cormier’s crew. This view is from the new building so you can tell it’s quite tall.

On Saturday, September 11th, the piers were installed and backfilled.

That’s the progress for the week of September 5-11. We are getting there. Hope that you are enjoying these summaries!

Our Garage+ Project – Week Seven Update

Wow – we are almost two months into this building project now. This week (August 29 – September 4, 2021) was REALLY busy as you’ll see below. My photos focused on the more active stuff – so I hope you find them and the continuing saga of this project interesting.

First, I was able to get some shots on the interior work on the second floor.

Jon and and Jonny Victor (the father and son team of Ready Installs) showed up early to check out the project’s progress.

Jonny checking out door height.

Next, the first order of business on Monday, August 30th, was to get the deck header up. This involved installing an ice-water barrier (which the crew decorated with a muscle-man drawing of Raphael as it will never be seen again), and nailing the header.

Inside the garage, work on installing furring in the ceiling went on.

Early furring work in garage

At this point, we had a need to get some construction synchronized dance going. To start the deck we needed get the piers in for the deck – which required excavation and careful measurement. Also, the septic line needed to be started. Andy Cormier returned with his excavator and crew to do this. There were quite a few roots in the ground from a previously removed pine tree.

Once the trench was right, each 600-lb. pier was put in, and checked for accurate placement.

After this, Andy backfilled the trench.

Monday August 30th progress.

On Tuesday, August 31st, work continued apace. The framing of the deck began as well as work on a septic line and more.

When Andy was safely done, work could get going on the deck supports. Temporary supports were used and then the main deck supports were attached to the piers.

The sun sets on Tuesday’s progress.

Wednesday saw more of the same – deck progress. I was out so I did not get as many photos. The crew had to wrap it up early as the remnants of Tropical Storm Ida were coming with heavy rain predicted Wednesday-Thursday.

The crew here is framing up the deck roof overhang as Jonny gets the stairway landing area identified and cleared.
A shortened day (Sep 1st) with progress on the stairs and the deck area clear here.

Ah, but the rain came heavy – BUT – it was only overnight and gone by the morning of Thursday September 2nd – so happily work could continue on the deck and second floor in preparation for Saturday roofing.

Yay – work can go on!
Interior framing progress.
View of the stair stringers and temporary cross bracing.
Thursday mid-day progress was strong – deck roofing overhang was nearly done.
End of day Thursday had the roof all enclosed and ready for the roofers. The boards on the deck are temporary supports for the crews.

No construction happened Friday as the roofing crew was going to hit the ground running on Saturday. And hit the ground early they did at 7 AM!

Sun coming up on the roofing crew on Saturday, September 4th.

The roofing crew was done in 4 hours – and now we are ready for another good week. We did also work o Saturday with one of Jon’s patio specialists to define what our patio would look like and that should be very exciting and gorgeous – but you’ll have to wait to see that (like us).

All roofed in!

Thanks for taking a look here – and what do you think of the progress so far? We have a good ways to go, and as the Starks (and EVERY New Englander) says, “Winter is Coming”…so we are certainly wanting sooner than later.

For those of you who are wondering if I will EVER get back to hobby stuff, I will. I am using some time to rewrite and add onto my Aztec supplement for Buck Surdu’s Feudal Patrol in Mesoamerica (Civilizations Collide). New and improved (I hope).

Also, I am writing a good number of scenarios too. Plus, golf season is winding down in the next six weeks, so that’s happening too.

Tiny Painted Heroes

The Adventures of a 50-Something Tabletop Gamer, Game Design hobbyist, and full-time Software Engineer

Home of the Grumpy Gnome

Tinkering with Artwork and Ideas

Steve's Paint Brush

Grimdark model making and mini painting

Wargamesculptors Blog

Life, Golf, Miniatures, & Other Distractions

Dead Dick's Tavern and Temporary Lodging

Life, Golf, Miniatures, & Other Distractions

Guru PIGS Blog

Guru's thoughts on wargaming, life, and the universe!

Wisely lead... without a head!

History, Miniatures and Wargaming

Kuribo's Painting

Fallout, MESBG, and Hellboy Painting, Terrain, Dioramas, and Battle Reports

Don't Give Greg Ideas

Seriously, just don't

War Across the Ages, and other dark horrors

A discussion of miniatures collecting, painting and gaming.

Classic Warhammer 40K

Painting diary focused on Warhammer 40K 2nd ed., 5th ed. WHFB, related GW games, and miscellaneous whimsy

Colonel Mustard

WW2 Modelling in 1/72 Scale

Bogenwald

Random painting and terrain making.

Pat's 1:72 Military Diorama's

Scale diorama tips and ideas

Arcade Dreams

Building the Arcade Dream

P.B.Eye-Candy

Phil's 20th century wargame pages

SP's Projects Blog

A futile fight against entropy or 'Every man should have a hobby'? Either way it is a blog on tabletop wargames, board games and megagames

30mmdave

Wargaming Plausible reality?

Faith&Steel

dave's gaming adventures: faithandsteel.wordpress.com

The Imperfect Modeller

Miniature Figure Painting and Diorama Modelling

Double Down Dice

Painting miniatures and rolling dice!

Just Needs Varnish!

My ongoing wargames projects!

miniaturepopcorns

Sculpting some worlds

despertaferres

Wargaming with the ability of a dull nine year old

Dawn of the Lead

Miniature wargaming and the occasional zombie

Rantings from under the Wargames table

Wargames, Figures, Sculpting and Converting Miniatures

Simple as WaR

Miniatures & Terrains

Buck's Blog

Life, Golf, Miniatures, & Other Distractions

IRO aka Imperial Rebel Ork

- I model - therefore I am -

Azazel's Bitz Box.

Painting, Modelling, Miniatures, 1:6, Games... Whatever else I find interesting.

diggingforvictoryblog

Smallholding and Wargaming.......not always at the same time!

Shamutantis

Nørdblog numero uno

Harry Heckel

Writer/Game Designer

The Lost and the Damned

Fantasy, sci-fi and historical miniature gaming

sho3box

Toy soldier wargaming stuff.