Our Garage+ Project – Week Six Update

Last week (August 22-28, 2021) was a stop-and-go affair for the project. As I mentioned in my last post, Tropical Storm Henri hit us with wind and rain Sunday-Monday, so progress on work was delayed until Tuesday the 24th.

At that point, things went fast as you’ll see below – until Friday. There was a crack three-man crew of Raphael (supervisor), yet another Raphael, and Enrique who arrived and worked like men possessed. This despite that the weather was really hot all three days – mid-90 degrees Fahrenheit (32 to 36 Celsius for you metric folks). There is really no shade either in our yard.

Putting on the sill and building the first garage wall.
The two Raphaels mug for the camera after getting up the first LVL beam. On the left is the supervising Raphael.
Another view of the beam going up showing the ZIP system sheathing and tape.
Soon, three garage walls were framed and sheathed. Here you see Raphael in front, Raphael in the middle, and Enrique in the back.
Bracing was set, and then the first of the second-story floor joists was installed on top of the garage walls.
More floor joists were to follow.
At the end of Tuesday the 24th, this was the hard-won progress. Again, it was HOT.
On Wednesday the 25th, work began early on the second floor flooring.
We also got a delivery of more lumber…and a porta-potty!
Work started on the second floor gables and walls.
Raphael handles a sheet of sheathing with ease.
View from the street as the first gabled wall goes up.
Closer shot of the first second floor gabled wall. There is going to be a pretty tall ceiling in that room.
The hot sun sets, revealing Wednesday the 25th’s progress.
The deck side wall went up plus the strong LVL beam that will go over the glass doors. Again, did I mention it was HOT? AGAIN?
Close up view of the second floor deck/door side.
Raphael strikes a pose as the rafters take shape! The man has some guns!

At the end of the day, here below was the progress for the week – on Thursday.

Progress at the end of August 26th.

Friday the project got held up as we needed to get the deck piers excavated – and the excavator did not make it to the site. Also, the pre-fabricated concrete deck piers would need to be moved to the other side of the building, and they weigh about 600 lbs. each. Ironically, the heat broke Thursday night and Friday was nice and in the 70’s. But it is August, so….the heat will be back, even in September. Of course it could snow in October…

I’m looking forward to more progress coming during the week of August 29th to September 4th. Stay tuned!

Author: Mark A. Morin

This site is where I will discuss stuff that I find interesting and that includes family, friends, golf, gaming, and Boston sports!

24 thoughts on “Our Garage+ Project – Week Six Update”

  1. Its really coming along now. That is a seriously impressive garage. If I didn’t know better, I would think you’re putting in a barn instead. Its nearly as tall and wide as the barns I’ve seen in Ohio anyway!

    Liked by 2 people

    1. Be careful Roger, I had to fight to get it built as if it was habitable (an apartment) it would violate our town by-laws. So long games yes, living in it no! Plus IRO is done and his is certainly very cool I agree

      Liked by 1 person

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s