Our Garage+ Project – Week 12 Update

Week 12 saw work being done on both decks, and well as connection to the National Grid gas line. We also had Evandro Rodrigues from E&V Masonry (who works with Ready Installs) come out to lay out the paving stone areas and the proposed gas fire pit. They also placed the concrete floor in last week.

It’s a bit difficult to see, but the spray-painted orange lines designate the plan for paving stones. These patio stones will go under the garage deck and stairs, then connect to the house deck. The gas fireplace will be the round circle here.

Work continued on the house deck as you can see below.

The garage stairs were stabilized and set up for decking.

The stairs being braced and supports added.
Close up of previous shot.

On the garage deck, the Trex rain gutter system was installed. This will keep the patio underneath dry. It will feed into a gutter under the downspouts.

The downspouts fit between the joists (with some help).
Jon and Will prep the downspouts for Josh.
Josh Victor stapling in the downspouts.

After the downspouts were in, the membrane that will carry the water to them is installed with the proper slope and sealed.

You can see the membrane here (and Will’s head).
Top view of the deck.
Underneath view.

Friday was a very active day, as National Grid came in to excavate and place the gas line. We also had deliveries for the finishing of the garage deck and stairs.

National Grid begins cutting the street and sidewalk to excavate for the new gas line.
Cut that asphalt!
There’s a gas main here somewhere…
…found it!

The line went from the street to the back of the garage along the driveway. This will be a second line we will have, and will provide gas for the heating of the garage as well as the future fire pit. Below you’ll see some shots of the trenching, connecting, and the asphalt repair.

At the beginning of all this, Home Depot and Jonny Victor delivered a lot of the materials for the following week’s work – mainly for the garage deck and stairs.

As a side note of interest (well I found it cute), I’ll add the following. My daughter works in a hospital as a radiation therapist with cancer patients – and has early hours two weeks a month. I help, as she drops my granddaughter Tabitha off with me at 6 AM (which for a 4 year old is pretty early). I get her breakfast and generally have good quality time with her before I bring her to preschool. While waiting to get dropped off at 8 AM, the following happened – watch my granddaughter here enthralled with her “sparkly pants”. I admit, she makes a good case for them…

Anyways, back to the project! There is still a lot of work to go, but this was a busy week indeed. Hopefully, I’ll be able to share an even more active week on my next update. Thanks for looking and feel free to throw in your two cents (or whatever the equivalent is in your currency) in the comments section.

And I hope you enjoy your fashion choices as much as Tabitha does!